more than 1/4 
in. deep and remaining distinct under the water around the shore line 
for one year. Apparently, the reservoir will finally become water-tight 
at all elevations. 
The soil in which the four service reservoirs on the railway are built 
proved to be about the worst for such work. In its natural state on the 
prairie, after the excavation for the reservoir was completed, it filtered 
water at the rate of 3 ft. per day. Tamping and puddling still left a 
filtration of 12 in. per day, with a tendency to increase. Enough water 
filtered through the concrete to produce settlement and cracks. Finally, 
the concrete was water-proofed with two coats of soap, two of alum, 
and one of asphalt. This has made all the reservoirs water-tight. 
Elaterite, an asphalt paint made by the Elaterite Paint and 
Manufacturing Company, of Des Moines, Iowa, was used successfully 
on the Luna Reservoir. This paint is applied cold, and preliminary tests 
showed it to be quite efficient. 
The analysis of the soil is as follows: 
Loss on ignition 3.35 Silica 56.36 Oxide of iron 2.93 Oxide of 
aluminum 8.97 Calcium oxide 15.95 Magnesium oxide 0.98 Oxides of 
sodium and potassium 0.47 Carbonic acid 11.35 Sulphuric acid 0.11 
Chlorine 0.04 Manganese Traces ------ 100.51 Insoluble matter, 64.50 
per cent. 
_Pipe-Line Leakage_.--There is no measurable leakage from the iron 
pipe. By thorough inspection and measurement at the end of two years, 
leakage on the wood pipe, between Coyote and Bonito Creek, from the 
11-and 12-in. pipe, was found to be as follows: 
On 8.6 miles, 11-in. pipe, 146,600 gal. per day = 17,046 gal. per mile. " 
4 " 12 " " 14,829 " " " = 3,702 " " " 
The 7-1/2-in. pipe on this section appears to be leaking less than the 
12-in. pipe. Inspection and measurement of it are to be made in a short
time. 
There is no material leakage from the 10-and 16-in. pipe between 
Bonito Creek and Nogal Reservoir, as determined by velocity and 
volumetric measurements hereafter described. The greatest probable 
error in the velocity measurements would not exceed 1/2 per cent. If 
such error existed, and was all charged to leakage, it would amount to 
but 17,204 gal. per day, or 1,582 gal. per mile, out of a daily delivery of 
3,784,000 gal.; but the measured discharge of the pipe, as determined 
by the velocity, was 5.84 sec-ft., while the mean maximum volume of 
this water over the weir at the end of the pipe is recorded by the weir as 
5.88 sec-ft. 
From Coyote, east along the railway, the wood pipe is remarkably tight. 
The rate of leakage from it, as determined by 600 observations 
uniformly distributed, was as follows: 
11-in. pipe = 120 gal. per mile per day. 8-1/2 and 7-1/2-in. pipe = 268 " 
" " " " 
The maximum rate on 1 mile was 1,613 gal. The minimum found was 
zero. 
The observations were made by uncovering a joint and measuring the 
leakage therefrom for 10 min. A graduated glass measuring to drams 
was used. The rate of leakage varied from 5 drops to 45 oz. in 10 min. 
Of the joints uncovered 57% was found to be leaking. It is rather 
remarkable that, in the large leakage of the 11-and 12-in. pipe between 
Coyote and Bonito, only one out of every eight joints was leaking. This 
indicates a physical defect in such joints. The largest leak found on one 
joint was at the rate of 17[,?]280 gal. per day. Leakage between or 
through the staves is not measurable, as it is not fast enough to come 
away in drops unless there is some imperfection in the wood. 
The insignificant leakage of 120 gal., stated above, is from the 11-in. 
pipe in the pumping main between Coyote and Corona. The present 
maximum working pressure on it is 100 lb. per sq. in. All the figures 
given above include visible and invisible leakage, the latter being such
as does not appear on the surface. The visible leakage is but a small 
part of the total. 
Stopping the Leaks.--Generally, any ordinary leak is readily stopped by 
pine wedges. Sometimes a loose joint requires individual bands bolted 
around it. Bran or saw-dust is effective in stopping the small leaks 
which cannot be reached by the wedges. The good effect of the latter is 
likely to be destroyed by a rapid emptying of the pipe. If the water is 
drawn out faster than the air can enter through the air-valves, heavy 
vacuums are formed down long slopes, and the air forces its way in 
through the joints and between the staves. The result is that the pipe 
will frequently leak badly for some time after it is refilled, although it 
may have been tight previously. 
A full pipe and    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
 
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.
	    
	    
