could be 
run across the floor to where you please, facilitating storage and 
dispensing with handling. This would not be possible with the cable. 
Comparing electricity and cable on this point, all things favor the 
former clearly and beyond all question. Furthermore, if locality so 
favored, the subject of land purchase for electricity could be tabooed 
entirely, since distance can be so readily overcome. Way out in the 
suburbs or back in the country by the side of some waterfall, your 
station might be, while the current is sent to the great city over heavy 
conductors. Here land rent or tax would be at the minimum. With 
horses or cable plainly proximity must be had. It is estimated that the 
land occupied by the Madison Avenue line of New York City is worth
the cost of 40 miles of ordinary double track. 
3d. Equipment at station and rolling stock. 
The rolling stock would be in each case approximately the same. 
Consisting of cars of equal seating capacity, the difference of cost 
would be the necessary attachments for the mechanical systems. 
A first class 16 foot horse car costs $1,200; A first class 16 foot cable 
car costs about $1,800; and A first class 16 foot electric car costs about 
$2,200. Rates: Electricity, 1; horse, 0.54; cable, 0.81. 
I believe, however, that the mechanical system is bound to work 
material changes in car construction, in fact it is almost imperative. In 
all probability a car with 15 to 20 per cent. greater seating capacity than 
the horse car can be constructed on a different plan for the price given 
for the electric car. This price, it must be noted, is the one for 
attachment of motor to the present horse car. The horse cars produced 
to-day are most carefully planned, thoroughly built, and admirably 
adapted to their service, but the inexorable law of progress decrees their 
extinction, for something better. 
Motive power. To represent clearly the costs, etc., of the three systems 
under this head, let us assume a road. Take, if you please, a double line 
6 miles long, and operating 24 cars with speed of 6 miles an hour, and 
running 20 hours out of 24. This would call for 48 horses on the track 
and 192 horses in the stables, or a total of 240 horses; at $160, counting 
harness, etc., this would cost $38,400. 
With electricity we will proceed as follows: The weight of car with 30 
passengers and motor attachments would be about 9,000 lb. It is easily 
calculated that to propel the same at the specified rate on a level would 
take about 1.75 horse power, a total of 42 horse power. To make 
allowances for grades we can calculate that, if the entire road was one 
gradient of three per cent., each car would take about 6.4 horse power, 
or since only 12 are going up, a total of 76.8 horse power. It will be fair 
now to take the average of these two, or 59.4 horse power for an 
average road. Allowing 35 per cent. loss from engine to work done in
actually propelling car, we would have to have 91.3 horse power. 
Allowing a good safety factor, it would be well to put in a 150 horse 
power plant. This would cost complete $7,000; necessary dynamos, 
$3,500. Among these figures should be counted cost of conductor of 
sufficient size to allow of but three per cent. in energy to overcome its 
resistance. This I have calculated using a potential of 600 volts; and 
find that the total cost of six miles copper conductor is $16,000 with 
above conditions. The total cost is now seen to be $26,500. 
As to cables, since the recovery of energy available for tractive 
purposes is but 35 percent., then the engine of 169 horse power 
represents what must be had. Allowing a generous factor of safety, let 
us say that a 250 is all sufficient. This would cost complete and erected 
about $12,000. The cable would cost $15.000, and gears, etc., $8,000, 
making a total of $35,000. 
The ratio of the three systems stands: Electricity, 1; cable, 1.09; horse, 
1.45. 
4th. Construction of tramway. 
Figures upon this point must necessarily be either averages or 
approximations. The nature of the locality socially, naturally, and we 
grieve to say it, politically, has a strong influence upon its construction. 
Estimating on single track only, a horse road would cost as an average 
$9,000 per mile. With electricity we have several methods we can avail 
ourselves of: Surface, costing about $10,000; overhead double 
conductor, $15.696; underground, $23,500. 
With cable but one method, the underground, is possible. This cost is 
variously estimated at from $30,000 to $110,000 per mile; however, the 
latter figure is excessive. A fair average would be $35,000. 
The ratio of    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.